It
has been 40 years since the skyline has changed at NASA’s
John C. Stennis Space Center, but a new 300-foot rocket
engine test stand is beginning to rise above the trees.
Fabricated steel began arriving by truck Oct. 24 for
construction of the A-3 Test Stand that will be used to test
the engine for the nation’s next generation of moon rockets.
After staging work was completed, workers from Lafayette
Steel Erector Inc. started assembling the 16 steel
“sequences” or stages on the stand foundation and footings
poured during the previous year.
By the time the initial phase of construction is complete in
April 2009, some 4 million pounds of fabricated steel will
be in place – and Stennis Space Center will have a towering
structure that will be used to test the J-2X engine in
development, said Robert Ross, deputy project manager for
the A-3 Test Stand. That engine will help send humans back
to the moon and possibly beyond.
Work on the A-3 Test Stand began with groundbreaking
ceremonies in August 2007. At that time, NASA Deputy
Administrator Shana Dale spoke of the historic nature of the
project.
"Groundbreakings are about new beginnings," Dale said. "The
first stand was erected at Stennis to test the Saturn V
rocket of the Apollo Program. Testing of the space shuttle
engines began here in the mid-1970s. And today, we're
breaking ground for a new test stand, for the new spacecraft
of a new era of exploration."
A
pair of new rockets are being developed as part of NASA’s
Constellation Program -- the Ares I crew launch vehicle and
the Ares V cargo launch vehicle. In addition to helping
humans go back to the moon and possibly beyond, the
Constellation spacecraft will be used to send astronauts to
the International Space Station. The new J-2X engine will
help power both vehicles.
The engine will be required to start at high altitudes.
However, none of the existing test stands at Stennis could
simulate altitudes of the sort that were needed. Thus, the
A-3 Test Stand is designed to test the new engine at sea
level and to simulate altitudes up to 100,000 feet.
The design also calls for the new stand to withstand 1
million pounds of thrust. As Ross explained, although the
J2-X will produce less than that at 294,000 pounds, "who
knows what may be needed in the future."
In addition to steel work under way, Stennis engineers are
scheduled to award a contract for test cell diffuser work in
January. A contract to complete the general work of the
project is scheduled to be awarded in February.
Coordinating the work of all the companies throughout the
upcoming months poses one of the biggest challenges, Ross
noted. "It's just going to take a lot of integration between
contractors," he explained.
In
addition, Stennis engineers are focusing on ensuring all
NASA-supplied equipment and materials are on hand when
needed, which is a challenging task. At the same time work
is progressing on the steel fabrication, contractors are
initiating construction of docks needed to deliver
propellants to the A-3 stand.
Two docks -- one for liquid hydrogen delivery and one for
liquid oxygen delivery -- are being built. That work is
scheduled to be complete in April 2009 as well.
Ross acknowledged delays have caused some to question the
status of the project. However, he said all is on schedule
to meet the May 2011 "need" date for the stand's completion.
"This is a tremendous time for everyone involved with the
space program," Ross said. "Like everyone else involved, I
feel lucky to be part of this project. For the rest of our
lives, we’ll be able to look at the stand and all it enabled
and say, 'I worked on that.'"